Milton, FL
The Federal Emergency Management Agency (FEMA) directed the United States Army Corps of Engineers (USACE) to develop and install recovery centers in response to the impact of several devastating hurricanes and Florida’s need for emergency assistance.
Under the Omaha Rapid Response contract, Conti was tasked with the design and construction of a temporary trailer site, Carmell Ridge, to be used for emergency housing of hurricane-displaced residents.
Conti was the general contractor for this time-sensitive housing construction mission, quickly mobilizing within 24 hours of receiving the task order and performing on a 12-hour a day, 7-day a week schedule to rapidly, with up to 60 people on site, achieve timely substantial completion.
The project included site preparation, permitting, design of infrastructure and utilities (including power, water, gas, sewer and storm drainage), site development and grading, laying pathways for and installing utilities and transport and installation of fifty-two 14-foot by 70-foot trailers for the temporary trailer park. Conti also supported getting the Land Use Development permit in place.
The team held daily site coordination meetings to discuss the next day’s activities and address health and safety. The latest technology was used to remotely report daily site activities including weather, meetings, work performed, materials received, test results and field measurements. The project was completed on schedule with zero safety incidents.
“[Conti’s] extremely long hours and dedication made this project exceed objectives.” - Mark Herse, USACE Operations Manager
Client | FEMA and USACE Omaha |
---|---|
Value | $3.2 M |
Status | |
Key features | |
|
Israel’s primary spaceport and one of its most technologically advanced air force bases requires the most up-to-date facilities to operate on the highest level.
Conti mobilized 100% of project crews within four days to clear 174,000 tons of hurricane waterway debris along the Atlantic Coast.
The tunnels, part of a system used to supply the heating and cooling for a large number of government buildings in the Washington, DC area, were built in the 1930s and required significant upgrades to meet today’s standards.